Technical Precision. Controlled Process.

As one of the fundamental stages of our manufacturing operations, the molding process is planned and carried out in accordance with customer technical drawings, specifications, product requirements and specific project requirements. With our in-house tooling infrastructure, we develop and manufacture tooling solutions within our own facilities, while carrying out the necessary controls throughout the process, from the selection and inspection of raw materials to forming and laboratory verification. This ensures that each production process progresses in a controlled manner in accordance with defined technical and quality criteria.

In-House Tooling

KALIP ALTYAPISI

In-house tooling solutions for our products

Series & Custom Projects

ÜRETİM KAPSAMI

Series production and customer-specific projects

Integrated Process

PROSES YÖNETİMİ

Coordination of tooling, compounding and production processes

Process flow07 step
  1. Mold Design and Manufacturing
    01

    Mold Design and Manufacturing

    The molds required for our series production products and customer-specific projects are prepared in-house. Mold solutions are developed according to product requirements, manufactured internally and subject to the necessary checks before being released for production.

  2. Raw Material Selection
    02

    Raw Material Selection

    The appropriate rubber type and required auxiliary materials are determined in accordance with the requirements specified in the customer’s technical drawing, specifications and special requests.

  3. Raw Material Inspection
    03

    Raw Material Inspection

    The conformity of the raw materials to be used, batch/lot information and required incoming inspection results are verified. Materials that have passed the required checks are released for the production process.

  4. Raw Material Forming
    04

    Raw Material Forming

    Following the completion of incoming inspections, the rubber material is formed into sheets, strips or other required forms suitable for the subsequent production process.

  5. Laboratory Testing
    05

    Laboratory Testing

    The necessary laboratory inspections and tests are performed to verify that the prepared rubber material meets the specified technical requirements. Depending on the requirements, tests such as hardness, density, rheometer (T90/TS2), tensile strength, elongation at break, compression set and other relevant tests may be performed.

  6. Evaluation of Results
    06

    Evaluation of Results

    Laboratory test results are evaluated against customer technical requirements, technical drawings, specifications and applicable internal acceptance criteria.

  7. Approval and Release to Production
    07

    Approval and Release to Production

    Material that has been verified as conforming is approved for use in the production process and transferred to the relevant production stage. For non-conforming materials, the necessary corrective actions and re-inspection procedures are carried out.

Request

Couldn't find the part you need?

Request a quote with a technical drawing or OEM number.